Defect Stage
Responsibility
Activities
Defect is entered
QA
  • The initial state is always NEW
  • It is unassigned  (Assigned to Dev Manager)
  • Email will be sent to the  Team
Triage Discussion
QA / DEV / PM
  • Prioritize defects brought into Triage meeting
  • Determine which Release/Build the fix will be made in
  • Assign defect to relevant team member.
Assignee
DEV
  • Due to automatic notification via email from the defect database, the assignee knows they have been assigned for a defect.
  • Reproduce the defect, change status to OPEN
  • Recognize the bug and change status to 'Duplicate' of another bug and specify what it is a duplicate of
  • Reproduce bug, recognize problem, make fix, unit test, check in code and change status to 'Fixed'
Defect  Verification
QA
  • Evaluate fixed bugs – ensure that they are fine working
  • Evaluate reproducible steps.
  • Verify fixed bugs Ã  move to Closed
  • OR move back to Re-Open state, if the fix failed